During the months of December 2020 and January 2021 IPMA CONSULTORIA has performed the related works corresponding to Pull Out Test for a Photovoltaic Solar Plant in Tangier, Morocco.

For this purpose, a field work campaign was designed based on:

  • Direct pile Ramming
  • Predrill pile Ramming
  • Pull Out Test
  • Shear test

Following the completion of the field campaign, several drawings have been developed that graphically show the results obtained.

These extrapolations allow the client to obtain a global idea of the behavior of his structure within the site and, in addition, show the problem areas:

In the following example, it can be recognized how, the central-eastern area of the plot shows a higher point resistance when direct driving is performed: